Bid Abstract

148748 (SAP 010-599-021) - 16TH STREET BRIDGE PROJECT (10J12)Landwehr Construction, Inc. Midwest Contracting, LLC Molnau Trucking LLC Rachel Contracting, Inc 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$11,750.00$11,750.00$24,000.00$24,000.00$20,000.00$20,000.00$47,300.00$47,300.00
2101.501CLEARING & GRUBBINGLS1$1,475.00$1,475.00$1,000.00$1,000.00$2,000.00$2,000.00$5,370.00$5,370.00
2104.502SALVAGE SIGNEACH3$110.00$330.00$50.00$150.00$250.00$750.00$27.00$81.00
2104.502SALVAGE MAIL BOX SUPPORTEACH1$110.00$110.00$125.00$125.00$250.00$250.00$111.00$111.00
2104.502REMOVE SIGNEACH2$110.00$220.00$50.00$100.00$250.00$500.00$27.00$54.00
2104.503REMOVE METAL CULVERTL F100$7.40$740.00$10.00$1,000.00$37.00$3,700.00$4.70$470.00
2104.504REMOVE BITUMINOUS PAVEMENTS Y42$10.00$420.00$4.00$168.00$45.00$1,890.00$3.40$142.80
2105.507COMMON EXCAVATION (P)C Y354$6.00$2,124.00$6.00$2,124.00$10.50$3,717.00$23.30$8,248.20
2118.509AGGREGATE SURFACING CLASS 1TON205$31.00$6,355.00$24.00$4,920.00$42.00$8,610.00$28.90$5,924.50
2360.509TYPE SP 12.5 WEARING COURSE MIX (2;B)TON10$225.00$2,250.00$250.00$2,500.00$71.00$710.00$229.50$2,295.00
2412.50212X7 PRECAST CONCRETE BOX CULV END SECTEACH2$18,540.00$37,080.00$20,000.00$40,000.00$17,600.00$35,200.00$18,200.00$36,400.00
2412.50312X7 PRECAST CONCRETE BOX CULVERTL F44$1,240.00$54,560.00$1,200.00$52,800.00$1,318.00$57,992.00$958.00$42,152.00
2442.501REMOVE EXISTING BRIDGELS1$6,650.00$6,650.00$4,500.00$4,500.00$5,000.00$5,000.00$5,870.00$5,870.00
2451.507COARSE AGGREGATE BEDDING (CV) (P)C Y95$67.00$6,365.00$75.00$7,125.00$37.00$3,515.00$75.00$7,125.00
2451.607STRUCTURAL BACKFILL (P)C Y190$33.50$6,365.00$35.00$6,650.00$37.00$7,030.00$45.00$8,550.00
2501.50215" GS PIPE APRONEACH2$270.00$540.00$150.00$300.00$250.00$500.00$530.00$1,060.00
2501.50218" GS PIPE APRONEACH1$300.00$300.00$175.00$175.00$300.00$300.00$563.00$563.00
2501.50318" CP PIPE CULVERTL F100$25.00$2,500.00$30.00$3,000.00$75.00$7,500.00$91.00$9,100.00
2501.50315" CP PIPE CULVERTL F120$19.50$2,340.00$28.00$3,360.00$55.00$6,600.00$83.00$9,960.00
2511.504GEOTEXTILE FILTER TYPE 7S Y525$2.40$1,260.00$4.00$2,100.00$4.50$2,362.50$6.90$3,622.50
2511.504GEOTEXTILE FILTER TYPE 5S Y180$2.00$360.00$3.00$540.00$3.50$630.00$4.00$720.00
2511.507RANDOM RIPRAP CLASS IIIC Y274$91.00$24,934.00$85.00$23,290.00$95.00$26,030.00$93.00$25,482.00
2540.602INSTALL MAIL BOX SUPPORTEACH1$220.00$220.00$150.00$150.00$200.00$200.00$139.00$139.00
2563.601TRAFFIC CONTROLLS1$1,350.00$1,350.00$2,000.00$2,000.00$3,500.00$3,500.00$1,330.00$1,330.00
2564.602INSTALL SIGNEACH3$75.00$225.00$150.00$450.00$200.00$600.00$139.00$417.00
2572.503TEMPORARY FENCEL F60$8.50$510.00$6.00$360.00$58.00$3,480.00$2.60$156.00
2573.503FLOTATION SILT CURTAIN TYPE MOVING WATERL F25$22.00$550.00$30.00$750.00$55.00$1,375.00$48.30$1,207.50
2573.503SILT FENCE; TYPE MSL F1,235$2.80$3,458.00$2.50$3,087.50$2.00$2,470.00$2.60$3,211.00
2573.503SEDIMENT CONTROL LOG TYPE WOOD FIBERL F120$3.00$360.00$2.50$300.00$4.50$540.00$3.30$396.00
2575.504RAPID STABILIZATION METHOD 4S Y520$2.00$1,040.00$2.00$1,040.00$4.50$2,340.00$2.50$1,300.00
2575.523RAPID STABILIZATION METHOD 3MGAL4$950.00$3,800.00$1,000.00$4,000.00$400.00$1,600.00$778.00$3,112.00
 Totals for project 148748 (SAP 010-599-021) $180,541.00 $192,064.50 $210,891.50 $231,869.50
 
Contract Total:$180,541.00$192,064.50$210,891.50$231,869.50