Contract Bid Abstract

108591 (SAP 010-643-012) - ALTERNATE #2- CSAH 43 Bridge and Approaches over Carver CreekMinger Construction Inc. Midwest Contracting, LLC 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$38,825.00$38,825.00$48,000.00$48,000.00
2101.511CLEARING AND GRUBBINGLS1$3,335.00$3,335.00$2,500.00$2,500.00
2104.501REMOVE FENCEL F1,324$1.55$2,052.20$1.00$1,324.00
2104.505REMOVE BITUMINOUS PAVEMENTS Y1,631$3.70$6,034.70$4.00$6,524.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F60$9.45$567.00$5.00$300.00
2104.523SALVAGE MAIL BOX SUPPORTEACH1$115.00$115.00$75.00$75.00
2105.501COMMON EXCAVATIONC Y1,300$7.65$9,945.00$4.00$5,200.00
2105.522SELECT GRANULAR BORROW (CV)C Y1,893$16.00$30,288.00$19.00$35,967.00
2105.522SELECT GRANULAR BORROW MOD 10% (CV)C Y5,664$16.00$90,624.00$19.00$107,616.00
2105.523COMMON BORROW (LV)C Y3,250$10.80$35,100.00$10.00$32,500.00
2211.501AGGREGATE BASE CLASS 5TON983$21.35$20,987.05$19.00$18,677.00
2221.501AGGREGATE SHOULDERING CLASS 3TON230$26.85$6,175.50$15.00$3,450.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (2,C)TON351$173.60$60,933.60$160.00$56,160.00
2360.502TYPE SP 12.5 NON WEAR COURSE MIX (2,B)TON234$135.75$31,765.50$125.00$29,250.00
2412.51116X10 PRECAST CONC BOX CULVERT END SECTIONSEACH4$21,280.00$85,120.00$30,000.00$120,000.00
2412.51116X10 PRECAST CONCRETE BOX CULVERTLN FT208$1,380.30$287,102.40$1,990.00$413,920.00
2442.501REMOVE EXISTING BRIDGELS1$7,500.00$7,500.00$20,000.00$20,000.00
2451.509AGGREGATE BEDDING (CV)C Y449$36.70$16,478.30$50.00$22,450.00
2511.501RANDOM RIPRAP CLASS IIIC Y304$82.65$25,125.60$81.00$24,624.00
2511.515GEOTEXTILE FILTER TYPE IV (MOD)S Y528$1.95$1,029.60$3.00$1,584.00
2540.602INSTALL MAIL BOX SUPPORTEACH1$135.00$135.00$75.00$75.00
2557.501WIRE FENCE DESIGN SPECIALL F557$3.35$1,865.95$4.00$2,228.00
2557.603BARBED WIRE FENCEL F787$5.55$4,367.85$4.00$3,148.00
2563.601TRAFFIC CONTROLLS1$5,350.00$5,350.00$6,000.00$6,000.00
2573.502SILT FENCE, TYPE MACHINE SLICEDL F1,650$1.55$2,557.50$1.50$2,475.00
2573.505FLOTATION SILT CURTAIN TYPE MOVING WATERL F100$17.25$1,725.00$20.00$2,000.00
2573.512TEMPORARY DITCH CHECK TYPE 2L F182$3.55$646.10$4.00$728.00
2575.572RAPID STABILIZATION METHOD 4S Y5,498$1.45$7,972.10$2.00$10,996.00
 Totals for project 108591 (SAP 010-643-012) $783,722.95 $977,771.00
 
Contract Total:$783,722.95$977,771.00